Logging of protection forest and site preparation work
within Sendai Nuclear Power Plant site


August 8, 2015
Pine woods of protection forest were spreading here.


May 2, 2018


June 2, 2018


August 12, 2018


August 12, 2018
Sedimentation basin


August 12, 2018
Pipe arrangement from the sedimentation basin


November 15, 2018


January 13, 2019


Currently underway protection forest cancellation application area
(the place surrounded by a red circle) and site preparation map


The place where logging of the protection forest and embankment construction work (the place
surrounded by a red circle) is done is the planned place for logging at the time of addition of Unit 3 and
it is the planned place of embankmentx construction work. (Environmental Impact Assessment Report)


Currently, the position of the sedimentation basin installed at the side of the embankment coincides with
the position of the retention basin at the time of Unit 3 expansion (the place surrounded by a green circle).
The position of the pipe arrangement from the sedimentation basin matches the position of the piping extending
from the retention basin (red line) at the time of Unit 3 expansion. (Environmental Impact Assessment Report)


Construction procedure of "15 months after start of preparatory work" of Unit 3.
(Environmental Impact Assessment Report)